1. Drain structure and remove old material that is loose on the structure, either by sand blasting or hand-grinding. Patch and fill with appropriate patching compound. Acid wash to remove excessive debris and to open pores in surface for better primer adhesion. Rinse y pressure washing.
|
|
2. Mask areas of the structure not to be sprayed with masking tape, vinyl sheeting. Roll on the Hydro Stop Sealer Primer, covering 300-400 sq. ft. per gallon. Drying time is approximately 2-3 hours to the touch, greatly dependent on the air temperature and humidity. Usually one coat of primer is sufficient. Total thickness is approximately 2-4 mils. Applicatoin of Finish Coat within 6 hours, no primer is needed, after 6 hours 2836 should be sparyed. While sealer is still tacky is the best time to apply Finish Coat. Applicator can wear golf shoes.
|
|
3. Spray the finish coat in small sections, overlapping the coverage and building up a thickness in 5-7 mils. per pass. Coverage is 30-50 sq. ft. per gallon. Drying time is approximately 15-30 minutes to touch, and one hour until walking on the surface. Total thickness is 15-18 mils. Finish Coat is sprayed on at 30 sq. ft. per gallon for a 15-18 mil thickness.
|
|